New Skate and BMX facility build jumps into action

The City's new skate and BMX facility is progressing well, on track for completion in September.

New Skate and BMX facility build jumps into action
Jul 15 2022

The City’s new skate and BMX facility is on track to open in spring, with a range of elements now in, and progress on the skate bowls underway.

Elements now installed at the facility include a Euro-Gap/kink ledge, tabletop combo, step up box jump, mellow across/down rail, mellow down bank with hubba, 5-stair with rail, A-frame with down rails, small box jump, bank, level change box jump and rail jam.

Construction of the 5-7 foot bowl and horseshoe bowl is progressing well and building of the BMX jumps and return track is scheduled to commence by the end of July.

Subject to weather, the project is on track for completion in September 2022.

The new $2.5 million development is funded by the State Government through METRONET.

The popular existing community facility based at Wotton Reserve, Embleton, is being relocated within the reserve to make way for the future Morley train station multi-storey car park.